Project Planning – Links between jobs

Direct Planning Project lets you create links to show the precedence of jobs scheduled for different resources.

Direct Planning Project - Links between jobs of a project

Direct Planning Project – Links between jobs of a project

Kinds of links

Links between jobs are end-to-start links, that may be of several kinds:

  • Classical link: target job can only start when source job is over.
  • Link with overlapping: target job can start before source job is over.
  • Link with shifting: target job can only start after the source job has finished for some time (security time, transportation time, sub-contracting time, etc.)
Direct Planning Project - Creating a link with shifting

Direct Planning Project – Creating a link with shifting

Modeling sub-contracting

Using the links with shifting, together with milestone jobs, enable modeling sub-contracting in the schedule. To model a return from sub-contracting earliest start date.